Virginia Coal Ash CCR Permit Program: What Generators Need to Know Before July 6, 2026

Virginia Coal Ash CCR Permit Program: What Generators Need to Know Before July 6, 2026

EPA proposes Virginia's partial CCR permit program. Utilities have 62 days to comment. Here's what approval means for compliance, enforcement, and closure planning.

On May 4, 2026, the EPA published a proposed approval of Virginia’s partial Coal Combustion Residuals (CCR) permit program—and utilities in Virginia now have 62 days to decide whether to comment. The July 6, 2026 deadline is not a suggestion. It’s the regulatory gate that determines whether the state program moves forward as written, or whether federal concerns force modifications before finalization.

This matters because Virginia’s approval is “partial”—meaning facilities will operate under a hybrid federal-state compliance regime. Utilities and independent power producers (IPPs) generating coal ash in the state won’t be fully delegated to Virginia oversight; instead, they’ll split compliance obligations between Virginia DEQ rules (which reflect federal standards through December 2020) and remaining federal mandates (the 2024 and 2026 amendments EPA finalized after Virginia’s regulations froze).

For plant managers and environmental directors, this creates operational complexity: two regulatory bodies, two sets of deadlines, two penalty regimes. Get it wrong, and you’re looking at $93,058 per day in federal RCRA Subtitle D penalties, plus state enforcement action.

Here’s what you need to know—and what the July 6 deadline means for your facility.

What Virginia’s CCR Program Approval Actually Means

The EPA is proposing to approve Virginia’s state permit program under RCRA Section 4005(d). Once finalized (likely Q4 2026 or Q1 2027), Virginia’s Department of Environmental Quality (VADEQ) will administer CCR permitting and oversight for landfills and surface impoundments, in lieu of EPA’s direct federal program.

The keyword: in lieu of. This doesn’t mean federal law disappears in Virginia. It means VADEQ’s rules operate instead of EPA’s baseline regulations—but only for the provisions Virginia has adopted.

Here’s the structure:

Under Virginia’s approved program (if finalized):

Remaining under federal jurisdiction:

Why the split? VADEQ submitted its permit program application in June 2025 based on federal CCR standards as they stood in December 2020. The agency chose not to include the newer 2024 and 2026 federal amendments in its submission. EPA accepted that approach—partial approval is now standard for states adopting delegation incrementally.

The practical reality: your facility complies with both. Virginia handles the permitting machinery; EPA monitors your compliance with the newer technical amendments. Fail at either, and the penalty clock starts.

Who This Affects (8 Virginia Utilities, 25 Units)

Virginia is home to 25 coal combustion residuals disposal units at 8 utilities and independent power producers. The breakdown: 7 landfills and 18 surface impoundments.

Named facilities include:

  • Possum Point Power Station (5 CCR surface impoundments)
  • Chesterfield Power Station (2 surface impoundments + new CCR landfill)
  • Clinch River Power Station (2 surface impoundments)
  • Bremo Bluff Power Station (3 surface impoundments)

If you operate any of these facilities, or if you manage environmental compliance for a utility with unlined ash ponds in Virginia, the state program approval affects your permitting timeline, enforcement responsibility structure, and closure planning.

Even if your utility is based outside Virginia but transports CCR to Virginia disposal facilities, the state program applies to the receiving facility.

How Partial Approval Changes Your Compliance Calendar

The July 6 comment deadline isn’t just procedural noise. It’s the last chance to shape how Virginia’s program rolls out. But regardless of comments, here’s what the approval (if finalized) means operationally:

Permitting Transition

Once VADEQ’s program is approved and takes effect (estimated Q1 2027), any new CCR disposal unit or significant expansion requires a Virginia solid waste permit under 9VAC20-81. The application process mirrors federal standards:

  • Notice of Intent (NOI): Local government coordination and approvals
  • Part A: Site suitability assessment and physical boundaries
  • Part B: Design, operation, monitoring, closure, and post-closure care plans

Virginia regulations mandate a minimum 45-day public comment period, with public hearing at least 30 days after notice and comment extension at least 15 days post-hearing. This timeline is longer than EPA’s typical federal permitting.

Groundwater Monitoring Doesn’t Change

Your facility must install and maintain groundwater monitoring systems at active and inactive CCR units. Federal requirements on this are non-delegable. Detection monitoring must include boron, calcium, chloride, fluoride, pH, sulfate, and total dissolved solids (TDS). If statistical increases are detected, you move to assessment monitoring and corrective action planning.

The state program doesn’t modify these requirements—Virginia’s regulations incorporate federal groundwater protocols by reference.

Facility Evaluation Reports (FERs) Stay Federal

Both FER Part 1 (historical coal ash placement documentation) and FER Part 2 (physical site evaluation and CCRMU identification) remain EPA obligations with EPA deadlines:

  • FER Part 1: Due February 9, 2027
  • FER Part 2: Due February 8, 2028

Virginia’s approval does not extend these deadlines. Utilities must treat federal FER timelines as immovable—state program approval is a separate track.

Closure Timeline: 2031 Is Locked In

Unlined coal ash surface impoundments larger than 40 acres must close by October 17, 2031. This is a federal deadline that Virginia’s program does not modify.

However, Virginia’s program does add an overlay: closure plans must address state-specific provisions. Units within the Chesapeake Bay watershed face additional closure sequencing constraints; units in Giles and Russell Counties face enhanced closure requirements. These state mandates can affect closure cost and timeline.

The net effect: you must satisfy both Virginia’s local closure standards and federal October 2031 deadline. No state program can extend the federal deadline.

The Dual-Enforcement Trap: $93,058/Day

Here’s where partial approval creates real risk: you now have two regulators reviewing your CCR compliance, each with independent enforcement authority.

Virginia DEQ enforcement (under the state program):

  • Authority over violations of Virginia’s adopted 40 CFR 257 Subpart D baseline (9VAC20-81) and Virginia-specific closure provisions
  • State-level corrective action orders, permit modifications, penalties
  • Virginia does not have independent state RCRA penalties; violations often escalate to federal enforcement

EPA enforcement (federal non-delegated provisions):

Recent precedent: In 2022, EPA settled with Evergy Kansas Central for coal ash violations at a retired Kansas facility with a $120,000 penalty plus corrective action requirements. While not Virginia-specific, the penalty underscores enforcement momentum.

Citizen suit exposure: Environmental groups can file RCRA Section 7002 citizen suits for any CCR violation—groundwater, closure, monitoring, permitting—regardless of EPA’s enforcement priorities. Virginia facilities have already attracted environmental scrutiny; coal ash coalition groups monitor Virginia DEQ permitting.

For plant managers: compliance failure in either the state or federal track triggers penalties. A lapsed groundwater monitoring sample hits federal law. A closure plan amendment rejected by VADEQ creates a closure deadline miss, which hits federal law. The incentive structure is simple: zero tolerance for either regulator.

Why Virginia’s “Partial” Program Matters More Than Other States

Three states have EPA-approved CCR permit programs: Oklahoma (2018), Texas (2021), and soon, Virginia (pending). Why does “partial” matter?

Oklahoma and Texas both developed fuller state programs that adopt the federal standards in place at their submission date. Once approved, they operate more independently from federal oversight.

Virginia is choosing a different path: submit a partial program now (faster EPA approval), then adopt the 2024 and 2026 amendments in a second state rulemaking wave (12–18 months after federal finalization). This two-step approach gets state delegation authority sooner, but leaves generators in a compliance limbo until Virginia’s second-wave rulemaking completes.

The advantage for Virginia: faster delegation, faster state control, faster regulatory certainty.

The disadvantage for utilities: two separate compliance tracks, two enforcement regimes, and uncertainty about when/how Virginia will adopt the federal amendments.

If your facility is in Texas or Oklahoma, you’re operating under a single state framework. If you’re in Virginia, you’re managing a federal/state split.

The July 6 Comment Deadline: What It Actually Controls

The Federal Register document is open for comment through July 6, 2026. EPA will hold a hybrid public hearing on June 24, 2026, with speaker pre-registration due June 22.

What can comments address?

In scope for comment:

  • Whether Virginia’s regulatory framework is as protective as federal standards
  • Adequacy of Virginia’s groundwater monitoring protocols
  • Adequacy of VADEQ’s enforcement capacity and authority
  • Whether the scope of the partial approval (what Virginia regulates vs. what EPA retains) is appropriate
  • Concerns about specific facilities or units in Virginia
  • Requests for clarification on how federal/state jurisdiction overlaps

NOT in scope:

  • Requests to extend the federal closure deadline
  • Arguments that CCR regulation is unnecessary (the underlying CCR rule is final)
  • Generic anti-coal advocacy (the EPA is not reopening whether coal ash is regulated)

For utilities with Virginia operations, the strategic question is whether to submit comments. Industry groups (American Public Power Association, Edison Electric Institute) will likely submit. Individual facility comments carry weight with EPA, especially if they highlight specific operational concerns or data.

Upcoming Compliance Milestones: The Cascade Accelerates

Here’s the timeline utilities face:

  • June 22, 2026: Last day to pre-register to speak at EPA public hearing
  • June 24, 2026: EPA hybrid public hearing on Virginia program
  • July 6, 2026: Federal Register comment period closes
  • Q4 2026 – Q1 2027: EPA finalizes Virginia program approval (estimated)
  • February 9, 2027: FER Part 1 due (federal, non-negotiable)
  • February 8, 2028: FER Part 2 due (federal, non-negotiable)
  • February 10, 2031: Groundwater monitoring systems must be installed at all identified CCRMUs (federal deadline)
  • October 17, 2031: All unlined impoundments >40 acres must be closed (federal deadline)

The window between Virginia program approval (Q1 2027) and FER deadline (February 2027) is one month. Utilities cannot wait for state program finalization to begin FER work. The federal deadline moves at its own pace.

What Plant Managers and EHS Directors Must Do Now

  1. Audit your Virginia CCR units. If you operate or manage facilities with CCR disposal units in Virginia, obtain the current inventory of all landfills, surface impoundments, and inactive units. Confirm your facility is included in the state program scope.

  2. Review your FER status. Begin FER Part 1 documentation now. You have ~eight months until the February 9, 2027 deadline. If you haven’t started, this is the trigger to engage environmental counsel and technical consultants.

  3. Verify your groundwater monitoring program. Confirm that your facility has adequate monitoring wells at active and inactive units, and that sampling/analysis protocols align with federal requirements. Any gaps must be closed before the February 2031 deadline.

  4. Assess closure readiness. If you operate an unlined impoundment >40 acres, develop a closure timeline and cost estimate. The October 2031 deadline is firm. Regulatory approval (state or federal) cannot extend it.

  5. Consider whether to comment. If your facility faces specific Virginia program impacts (e.g., closure sequencing concerns, permitting complexity), consult your environmental counsel about whether submitting a comment is strategically valuable. The deadline is July 6, 2026.

  6. Track Virginia’s second-wave rulemaking. After EPA approves the partial program, expect VADEQ to propose adopting the 2024 and 2026 federal amendments. This will be a separate comment/rulemaking process. Mark your calendar to watch for Virginia Register notices in late 2026/early 2027.

  7. Plan for both state and federal compliance. Build into your compliance calendar: FER deadlines (federal), state permit timelines (state), and closure planning (both). Treat them as independent gating mechanisms.

Risk Categories for Virginia Utilities

Understanding what can go wrong helps focus compliance effort:

Groundwater contamination. If monitoring detects statistical increases in boron, chloride, or other indicator parameters, you’re obligated to shift to assessment monitoring and develop a corrective action plan. This is EPA’s highest-priority violation category and triggers immediate enforcement risk.

FER deadline misses. Part 1 is historical documentation; failure is significant but recoverable with explanation. Part 2 is technical—if your site evaluation is inadequate or misses CCRMU identification, you face a compliance gap that EPA will cite.

Closure delay. October 2031 is not flexible. If your closure design is not approved by EPA (or VADEQ once the program is live), you face operational shutdown orders and civil penalties.

Beneficial use violations. If you plan to use more than 12,400 tons of unlined CCR outside the facility (beneficial use), federal requirements apply. Virginia’s approval does not relax these requirements.

Permit modification delays. If you need to modify your existing permit for a closure plan, expanded monitoring, or dewatering system change, state permitting timelines (45-day comment period minimum) add timeline risk to federal deadlines.

For each category, advance planning reduces exposure.

The Regulatory Strategy: Virginia as a Model

Virginia is not the only state seeking CCR delegation. North Dakota and Wyoming both have pending or recently finalized partial programs. The pattern is clear: states are adopting delegation incrementally, which spreads compliance across multiple state rulemakings and creates ongoing regulatory uncertainty.

For utilities, this is a long-term condition, not a one-time transition. Expect Virginia to propose adopting the 2024 and 2026 federal amendments within 12–18 months of EPA’s approval. Then, if further federal amendments are finalized (the April 2026 proposal is still under comment), Virginia will face another rulemaking decision.

The implication: utilities with multi-state operations need a regulatory intelligence system. Virginia’s partial approval today is a precursor to fuller delegation tomorrow. Generators cannot assume today’s compliance framework is tomorrow’s.

What Comes Next

The EPA’s May 4, 2026 proposal is not a final rule. It is a proposal that EPA will refine based on comment, then finalize. The timeline suggests finalization in Q4 2026 or Q1 2027. Once finalized, VADEQ will implement the program and begin accepting state permit applications.

Utilities should expect:

  1. Comment period resolution (Q3 2026): EPA reviews comments, makes any modifications to the approval
  2. Final approval publication (Q4 2026 – Q1 2027): EPA publishes final approval notice in Federal Register
  3. State implementation (Q1 – Q2 2027): VADEQ begins accepting state permits for new/modified units; existing units remain under interim federal/state framework
  4. State second-wave rulemaking (late 2026 – 2027): VADEQ proposes adopting 2024/2026 federal amendments
  5. Ongoing federal oversight: EPA retains jurisdiction over 2024/2026 amendments, groundwater monitoring, FER deadlines, closure deadlines

For plant managers, the critical milestones are the FER deadlines (February 2027 and 2028) and the unlined impoundment closure deadline (October 2031). State program approval is the enabling mechanism, but federal deadlines are the gating constraints.

How iSi Helps Virginia Utilities Navigate This

CCR compliance under a partial state program requires coordinating federal and state deadlines, monitoring both EPA and VADEQ announcements, and building compliance strategies that satisfy two regulatory regimes.

iSi Environmental has deep experience with multi-state CCR programs (we’ve worked with utilities in Oklahoma, Texas, Kansas, and Missouri). We understand how partial delegation works, where compliance gaps hide, and how to sequence FER, monitoring, and closure planning to hit federal deadlines while managing state permitting timelines.

If you operate a Virginia CCR facility—or if you’re evaluating how Virginia’s program approval affects your environmental compliance strategy—schedule a brief call with our environmental compliance team. We can audit your current FER status, review your groundwater monitoring program, and map your closure timeline against both state and federal gating requirements.

The July 6 comment deadline is a threshold. The October 2031 closure deadline is the cliff. Everything in between requires a coordinated plan.


Key Takeaways

  • Virginia’s partial CCR program approval (proposed May 4, 2026) creates a hybrid federal/state compliance regime
  • 8 Virginia utilities operate 25 CCR disposal units affected by the program
  • Comment period closes July 6, 2026 (62 days from publication)
  • Virginia regulations reflect federal standards through December 2020; EPA retains jurisdiction over 2024/2026 amendments
  • Groundwater monitoring, FER deadlines (Feb 2027, Feb 2028), and closure deadline (Oct 2031) remain federal obligations
  • Dual enforcement exposure: VADEQ for state violations, EPA for federal violations—up to $93,058/day penalties
  • Utilities must plan for both state permitting processes and federal deadline compliance
  • Partial program approval is often a precursor to fuller delegation; expect Virginia’s second-wave rulemaking 12–18 months post-approval

iSi Environmental helps utilities, manufacturers, and industrial operators navigate complex multi-state CCR compliance. From Facility Evaluation Report support to closure design and regulatory liaison, we turn compliance complexity into competitive advantage. If your facility faces CCR deadlines in Virginia or elsewhere, let’s talk strategy.

Schedule a CCR Compliance Assessment